(a)GAO will consider protests concerning awards of subcontracts by or for a Federal agency, sales by a Federal agency, or procurements by agencies of the government other than Federal agencies as defined in § 21.0(c) if the agency involved has agreed in writing to have protests decided by GAO.
(b)The provisions of this part shall apply to nonstatutory protests except for:
(1)Section 21.8(d) and
(e)pertaining to recommendations for the payment of costs; and
(2)Section 21.6 pertaining to the withholding of award and the suspension of contract performance pursuant to 31 U.S.C. 3553(c) and (d). \[61 FR 39042, July 26, 1996, as amended at 83 FR 13825, Apr. 2, 2018\]